Brewery Upgrade Part Four B.
Insulation in place prior to the walls being spray painted with the airless sprayer and the colourbond cladding going on.
The walls have now been painted with the airless sprayer, the colourbond cladding and rollor door attached and the range hood installed. The rollor door is only being used to move large items such as fridges and tanks in an out of the brewery as it is behind where the brewing vessels are going.For everyday access there is a side entrance.
This is the motor for the range hood up on the roof.
My
Electric Brewery control panel is now bolted to the wall and powered up. confirming it is working.
This is looking towards to front half of the brewery showing the sink, rangehood, table for brewing vessels and control panel.
This is the back half of the brewery where the fermentation vessels and fermentation fridges will go. Note my red grain mill does crush grain faster.
This shot shows the brewing vessels on their table. They have not been plumbed in yet and the pumps are not installed.
My brite tank.
Some fermentes at the back along with the brite tank.
This shot shows a bit more plumbing attached to the brewing vessels. I still need to make a stand for my two pumps to be attached to.