Howdy all

So my upgrade project is very nearly complete. I've rebuilt almost everything, including the brew stand which i made from lumber which used to be my deck roof. This also made my work bench.

Noting my space limitations, i created a corner stand. I've never actually seen on in pics, but i really like how mine fits in.

I was also fortunate to find my fermentating chamber door is reversible. So i switched it across to make it easier to fill up - no more 5m hose needed!

new brew stand.jpg
switched door.jpg
 
From here i replaced my brewery control box. I eventually chose the Aubers pre-made Brew Buddy I. I asked them to modify it by adding an extra pump control point, and a power in which suits my existing plug (see previous post), and finally to use Aussie plugs. They were happy to oblige, for a small cost of course. I then had to figure how to install it. Noting the corner setup with a fridge in the way i only really had one option. So with the same left over lumber, i build a frame.

The pics below also show the tip frame i built for my mash tun. My objective with this rebuild was to make brewing easier and more self-contained (i.e. not dragging the pots to the garden to clean, and get covered in grass and mud). I'll soon be upgrading the sink i have access to, to one much bigger. That's the next project.
 

Attachments

  • 1733986617812.jpeg
    1733986617812.jpeg
    2.9 MB
  • frame complete.jpg
    frame complete.jpg
    1.4 MB
  • IMG_20241123_143004357_HDR.jpg
    IMG_20241123_143004357_HDR.jpg
    2.7 MB
And finally, the latest stage.

I decided on a 3 pump system so that i wouldn't have to remove any pipes or hoses during a brew. To accompany this i got a heap of SS piping. Idea was to connect everything from the pump upwards via SS. Turns out that's a bit tricky without access to a CAD and bespoke fittings. So i ended up mostly going from the pumps to the frame and using a flexible brewer piping for the jump to the pots.

I have purchased and installed (one more to do) 3-way valves, so that i just need to turn a couple when the brewing moves to the next stage. Hopefully i don't have too many leaks, as i've used a heap of plumbers tap!
Semi complete 3.jpg


Last thing to do is, get a couple more of the pipe connector thingies as i ran out, bend my heating elements - 5750w (they're about 3" too long!) and get a sparkie to wire up the elements and extend the cable with the control box in. Then happy brewing (although also need a new fermentator fridge controller).
 

Attachments

  • Semi complete 1.jpg
    Semi complete 1.jpg
    1.6 MB
  • Semi complete 2.jpg
    Semi complete 2.jpg
    1.2 MB
Nice setup. One question though, are those pumps set up correctly? Usually the inlet in through the middle and the outlet is on the side/too.
 
Crap, you are correct. Better fix that. Thanks for pointing it out.
 